Now comes a splash of color
Hello dear readers, we want to re-sign
times and describe the current state of affairs. In the last week is really a lot happening again, the inside of the slab on the floor is dry, the tiler of Danwood have almost everything done yesterday and the guys started to plaster our beautiful home.
But times of the front-floor company came last week, early Saturday morning at 9:00 clock the foreman to me that the squad will be at 16:00 clock again on the way to Berlin. OK ... I thought, imagine for a non-lay people, an entire house in the time-but I like to let myself be surprised. 15:30 I am driven to the house and the boys were actually on the premises together.
The flow installers can say nothing new, as the the same speed and working correctly, like all other trades by Danwood.
And then there is still the outside wall where we are today the result could examine. Had all fallen into the family ...
you yesterday had plastered all white, and today was the green part of the series. Scheeeeennnnnnn ........
Yes what can one say?
was a small lack of it well-but was changed within a day.
The gutter had been installed on the gradient ago in the wrong direction. To date
can say I only really positive about Danwood.
Then the builders are also times thank the good break supply, bring lunch every day for home delivery and coffee for all construction workers on site. (Thank you, Grandpa and Grandma)